Qualships Engineering was engaged to carry out permanent hull repairs on the port side shell plate and associated bracket at frame No. 77. The repair was executed onboard at anchorage under tight time constraints — and delivered in record turnaround time. Job Summary: • Damage Identified: Cracks observed on the shell plate and bracket at L51 longitudinal – Frame 77 (Port Side). • Repairs Carried Out: • Shell Plate Renewal – 915 mm × 815 mm × 18 mm, EH36 grade • Bracket Renewal – 830 mm × 420 mm × 18 mm, EH36 grade • Double-V weld preparation, ceramic backing applied • All welding performed by DNV-approved welders under WPS • Testing & Inspection: • Visual inspection and NDT (MT & Dye Penetrant) completed satisfactorily • Hydrostatic pressure test on No.8 Water Ballast Tank successfully conducted • Class approval granted by CCS upon inspection